The Executive Committee decided:
- To take note of the 2016 consolidated project completion report (PCR) contained in document UNEP/OzL.Pro/ExCom/77/7;
- To urge bilateral and implementing agencies to submit to the 79th meeting PCRs for multi-year agreements (MYAs) and individual projects that were due, and if they did not, to provide the reasons for not doing so and the schedule for submission;
- To urge cooperating implementing agencies to complete their portions of PCRs to allow the lead implementing agency to submit them according to the schedule;
- To urge bilateral and implementing agencies to enter clear, well written and thorough lessons learned when submitting their PCRs; and
- To invite all those involved in the preparation and implementation of MYAs and individual projects to take into consideration the lessons learned from PCRs when preparing and implementing future projects.