Decision 80/56

November 2017
UNDP | UNIDO | World Bank
Core unit costs

The Executive Committee decided:

  1. To note:
    1. The report on the 2018 core unit costs for UNDP, UNIDO and the World Bank contained in documents UNEP/OzL.Pro/ExCom/80/29,  UNEP/OzL.Pro/ExCom/80/29/Corr.1 and  UNEP/OzL.Pro/ExCom/80/29/Corr.2;
    2. The use of the revised format for reporting administrative costs by UNDP, UNIDO and the World Bank, pursuant to decision 79/41(e);
    3. With appreciation, that the World Bank’s core unit operation was again below its budgeted level and that it would be returning unused balances of US $62,476 to the Multilateral Fund at the 80th meeting;
  2. To approve the requested core unit budgets for:
    1. UNDP in the amount of US $2,069,385;
    2. UNIDO in the amount of US $2,069,385; and
    3. The World Bank in the amount of US $1,735,000.