Decision 83/61

May 2019
UNEP Compliance Assistance Programme | Core unit costs

Following informal consultations, the Executive Committee decided:

  1. To note the review of administrative cost regime: analysis by country, of project management units (PMUs), institutional strengthening, and implementing agencies, including activities and funding under the Compliance Assistance Programme, core units and other elements of the administrative cost regime, and information on national-level independent verification (decision 82/82(b)), contained in document UNEP/OzL.Pro/ExCom/83/39; and
  2. To request bilateral and implementing agencies, when submitting tranche funding requests for HCFC phase-out management plans, to include: in the tranche implementation plan, the specific activities that would be implemented by the PMU, and the associated funding; and in the implementation report of the previous tranche, the activities implemented by the PMU and the associated funding disbursed.