Decision 85/31

June 2020
China
World Bank
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To note the progress report on the implementation of the first tranche of the polyurethane (PU) foam sector plan of stage II of the HCFC phase-out management plan (HPMP) for China; and
  2. To approve the second tranche of the PU foam sector plan of stage II of the HPMP for China, and the corresponding 2020-2022 tranche implementation plan, in the amount of US $2,067,012, plus agency support costs of US $144,691 for the World Bank.