The Executive Committee decided:
- To note the final progress report on the implementation of the work programme associated with the first and final tranches of stage I of the HCFC phase-out management plan (HPMP) for Qatar, submitted by UNIDO and contained in document UNEP/OzL.Pro/ExCom/86/70; and
- To approve, on an exceptional basis, the extension of the completion date of stage I of the HPMP for Qatar, from 30 June 2020 to 31 December 2020, on the understanding that the project would be financially completed by 1 March 2021 and that an additional 0.41 ODP tonnes of HCFC-22 would be deducted from the country’s remaining HCFC consumption eligible for funding under stage II of the HPMP.