Decision 88/68

November 2021
China
DEU | JPN | UNEP
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To note the progress report on implementation of the third tranche of the servicing sector plan and the enabling programme under stage II of the HCFC phase-out management plan (HPMP) for China; and
  2. To approve the fourth tranche of the servicing sector plan and the enabling programme under stage II of the HPMP for China, and the corresponding 2022 tranche implementation plan, in the amount of US $2,229,613, consisting of US $1,160,000, plus agency support costs of US $127,291, for UNEP, US $600,000, plus agency support costs of US $71,122, for the Government of Germany and US $240,000, plus agency support costs of US $31,200, for the Government of Japan.