Decision 90/40

June 2022
Libya
UNIDO
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To note the submission of the progress report on the implementation of stage I of the HCFC phase?out management plan (HPMP) for Libya as requested in decision 82/75(c);
  2. To request UNIDO to submit the final progress report for stage I of the HPMP to the first meeting of the Committee in 2023;
  3. To approve, in principle, stage II of the HPMP for Libya for the period 2022–2027 to reduce HCFC consumption by 80.5 per cent of the country’s baseline, in the amount of US $2,170,268, plus agency support costs of US $151,919, for UNIDO;
  4. To deduct the additional 31.90 ODP tonnes of HCFCs phased out during stage I and the 24.87 ODP tonnes of HCFCs associated with stage II from the remaining HCFC consumption eligible for funding;
  5. To approve the Agreement between the Government of Libya and the Executive Committee for the reduction in consumption of HCFCs, in accordance with stage II of the HPMP, contained in Annex XV to the present report;
  6. To allow the submission of a foam sector plan during the implementation of stage II of the HPMP prior to 1 January 2024 in order to phase out the remaining consumption in the foam manufacturing sector; and
  7. To approve the first tranche of stage II of the HPMP for Libya, and the corresponding tranche implementation plan, in the amount of US $976,018, plus agency support costs of US $68,321, for UNIDO.
Related annexes
Annex XV to document 90/40, HPMP stage II agreement with Libya