Decision 91/38

December 2022
Ecuador | Niger
HFC enabling activities and investment projects | HFC cost funding guidelines including starting point | Kigali HFC implementation plans related | Kigali HFC implementation plan template Agreements

The Executive Committee decided:

  1. In the absence of the cost guidelines for HFC phase-down, to consider HFC individual investment projects and stage I of the Kigali HFC implementation plans (KIPs) on a case-by-case basis and without setting a precedent for the cost guidelines or any future HFC individual investment projects and stage I of KIPs;
  2. To consider the HFC individual investment project for Ecuador contained in document UNEP/OzL.Pro/ExCom/91/40 and stage I of the KIP for the Niger contained in document UNEP/OzL.Pro/ExCom/91/48 under agenda item 9(d) on projects recommended for individual consideration, in line with subparagraph (a) above;
  3. To request the Secretariat to prepare a draft template for an Agreement for stage I of KIPs for consideration by the Executive Committee at the 92nd meeting; and
  4. To agree that the template Agreement would be reviewed once discussions on the criteria for funding HFC phase-down had been completed.