The Executive Committee decided:
- To note the report on the disbursement of incremental operating costs under the industrial and commercial refrigeration and air-conditioning sector plan under stage I of the HCFC phase-out management plan for China, submitted by UNDP on behalf of the Government of China in line with decision 90/27 and contained in document UNEP/OzL.Pro/ExCom/92/9; and
- To note also that the remaining balance of the incremental operating costs of US $1,163,094, plus agency support costs of US $81,417 for UNDP, would be returned to the Fund after the approval of the financial audit report at the 93rd meeting.