Decision 92/30

June 2023
Indonesia
AUS | UNDP
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To approve, in principle, stage III of the HCFC phase-out management plan (HPMP) for Indonesia for the period from 2023 to 2030 for the complete phase-out of HCFC consumption, in the amount of US $16,048,056, consisting of US $13,240,847, plus agency support costs of US $926,859, for UNDP and US $1,685,000, plus agency support costs of US $195,350, for the Government of Australia, on the understanding that no more funding from the Multilateral Fund would be provided for the phase-out of HCFCs;
  2. To note the commitment of the Government of Indonesia:
    1. To phase out HCFCs completely by 1 January 2030 and to ban the import of HCFCs by 1 January 2030, except for those allowed for a servicing tail between 2030 and 2040, where required, consistent with the provisions of the Montreal Protocol;
    2. To ban the import, manufacture and installation of HCFC-123-based chillers by 1 January 2026;
    3. To ban the import, assembly and manufacture of HCFC-123-based fire‑suppression and fire-protection equipment no later than 1 January 2030;
  3. To deduct 184.59 ODP tonnes of HCFCs from the remaining HCFC consumption eligible for funding;
  4. To approve the Agreement between the Government of Indonesia and the Executive Committee for the reduction in consumption of HCFCs, in accordance with stage III of the HPMP, contained in annex XVI to the present report;
  5. That, to allow for consideration of the final tranche of its HPMP, the Government of Indonesia should submit:
    1. A detailed description of the regulatory and policy framework in place to implement measures to ensure that HCFC consumption was in compliance with paragraph 8 ter(e)(i) of Article 5 of the Montreal Protocol for the period 2030–2040;
    2. If Indonesia were intending to have consumption during the period 2030‑2040, in line with paragraph 8 ter(e)(i) of Article 5 of the Montreal Protocol, proposed modifications to its Agreement with the Executive Committee covering the period beyond 2030; and
  6. To approve the first tranche of stage III of the HPMP for Indonesia and the corresponding tranche implementation plan in the amount of US $4,319,049, consisting of US $3,520,244, plus agency support costs of US $246,417, for UNDP and US $495,000, plus agency support costs of US $57,388, for the Government of Australia.
Related annexes
Annex XVI to document 92/56, HPMP stage III agreement with Indonesia