Decision 92/32

June 2023
Suriname
UNEP | UNIDO
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To note the progress report on the implementation of the third tranche of stage I of the HCFC phase-out management plan (HPMP) for Suriname;
  2. To approve, on an exceptional basis given the delays in implementing phase-out activities, and noting that no further extension of project implementation would be requested, the extension, to 30 June 2024, of the date of completion of stage I of the HPMP for Suriname;
  3. To request the Government of Suriname, UNEP and UNIDO to submit a progress report on the implementation of the work programme associated with the final tranche to the last meeting of the Executive Committee in 2024 and the project completion report to the first meeting in 2025; and
  4. To approve the fourth and final tranche of stage I of the HPMP for Suriname and the corresponding 2023–2024 tranche implementation plan in the amount of US $25,065, consisting of US $13,500, plus agency support costs of US $1,755, for UNEP and US $9,000, plus agency support costs of US $810, for UNIDO, on the understanding that the Government of Suriname, UNEP and UNIDO would submit a status report on the implementation of the recommendations from the verification report to strengthen the licensing and quota system, as identified in paragraph 15 of document UNEP/OzL.Pro/ExCom/92/38, to each meeting of the Executive Committee starting from the 93rd meeting and that stage II of the HPMP for Suriname would be considered only after satisfactory implementation of the above recommendations.