Decision 93/16

December 2023
Jordan
World Bank
World Bank progress reports

The Executive Committee decided

  1. To note the progress report of the World Bank as at 31 December 2022 contained in document UNEP/OzL.Pro/ExCom/93/19
  2. To approve the extension, to 31 December 2024, of the completion date of stage II of the HCFC phase‑out management plan for Jordan (first tranche (JOR/PHA/77/INV/99); second tranche (JOR/PHA/84/INV/108); and third tranche (JOR/PHA/91/INV/113)), to allow completion of the remaining ongoing activities, as reflected in table 5 of document UNEP/OzL.Pro/ExCom/93/19; and 
  3. To approve the recommendations related to ongoing projects with specific issues contained in annex VII to the present report.
Related annexes
Annex VII to document 93/105, actions on ongoing projects with outstanding issues in the WB's progress report