Decision 93/89

December 2023
India
UNDP
Projects approved / deferred / transferred

The Executive Committee decided

  1. To approve the project proposal for the energy-efficiency pilot component included as part of the project for the conversion, in the manufacture of commercial refrigeration appliances at Rockwell Industries Limited, from the use of HFC-134a to propane as a refrigerant, in the amount of US $150,000, plus agency support costs of US $13,500, for UNDP, on the understanding:
    1. That the pilot component would be completed no more than 36 months after the date of approval by the Executive Committee;
    2. That a detailed project report would be submitted to the Executive Committee within six months of the date of completion of the investment project; 
    3. That data verified by an independent peer reviewer would be shared with other enterprises and made available to Article 5 countries, except for certain specific elements of proprietary information of the enterprise; and
  2. To note the commitment of Rockwell Industries Limited to continue to meet the voluntary energy-efficiency standards after the completion of the project.