The Executive Committee decided:

  1. To note the progress report of UNIDO as at 31 December 2023 contained in document UNEP/OzL.Pro/ExCom/95/18;
  2. To approve the extension, to 31 December 2025, of the completion date of stage II of the HCFC phase out management plan for the Sudan (first tranche (foam sector) (SUD/PHA/75/INV/38)) to allow completion of the remaining ongoing activities, as reflected in table 5 of document UNEP/OzL.Pro/ExCom/95/18; and 
  3. To approve the recommendations related to ongoing projects with specific issues contained in annex VIII to the present report.
     
Related annexes
Annex VIII to document 95/94, actions on ongoing projects with outstanding issues in UNIDO's progress report