The Executive Committee decided to approve the pilot project to maintain and/or enhance the energy efficiency of replacement technologies and equipment in the context of HFC phase-down (non-investment activities) for Peru, in the amount of US $115,000, plus agency support costs of US $14,950, for UNEP, noting: 

  1. That the Government of Peru had committed to the conditions referred to in decision 91/65(b)(iv)b. to b(iv)d.; and
  2. That the project would be operationally completed no later than 31 December 2027, and that a detailed project report would be submitted to the Executive Committee within six months of the date of completion of the project.