Decision 97/46

December 2025
China
World Bank
Projects approved / deferred / transferred

On the basis of the informal discussions and subsequent bilateral discussions, the Executive Committee decided

  1. To note the progress report on the implementation of the fifth tranche of the polyurethane (PU) foam sector plan of stage II of the HCFC phase-out management plan (HPMP) for China; and
  2. To approve the sixth tranche of the PU foam sector plan of stage II of the HPMP for China, and the corresponding 2026 tranche implementation plan, in the amount of US $5,000,000, plus agency support costs of US $350,000, for the World Bank.