102.     The Executive Committee approved the following projects to be implemented by the World Bank and the funds indicated:

 

Approved amount

US $

Conversion project at Argon Malaysia, Sdn. Bhd

131,200

Substitution of CFC-12 and CFC-11 with HFC-134a and HCFC-141b respectively and elimination of the use of 1,1,1, TCA in household refrigerator manufacturing at Matsushita Electric Co.

1,276,500

The Executive Committee noted that: (a) each project submitted should meet the guidelines and criteria established by the Executive Committee; (b) at its Thirteenth Meeting the Executive Committee had decided to grant the Bank permission to proceed with this project, with the incremental costs of the project being revised to take account of the Secretariat's and technical reviewer's comments and the project being resubmitted; and (c) the Bank had in fact addressed all of the issues and resubmitted the project. Approval was given on the understanding that the resubmitted project had been developed in accordance with the decisions of the Executive Committee.

 

Conversion of the aerosol filling plant Kontrak Manufacturing Services Sdn. Bhd

618,000