Decision in paragraph 111 in UNEP/OzL.Pro/ExCom/15/45

December 1994
Uruguay
World Bank
Projects approved / deferred / transferred

Project proosals:  Uruguay

111.     The Executive Committee approved the following projects to be implemented by the World Bank and the funds indicated:

 

Approved amount

US $ 

Elimination of the use of CFC-11 as a blowing agent in rigid polyurethane foam used as insulation in thermal tanks at Etchepare-Gil S.A.

235,050

Elimination of the use of CFC-11 as a blowing agent in rigid polyurethane foams used as insulation for refrigerators and substitution of CFC-12 used as refrigerant at Indurnor S.A.

448,140

Elimination of the use of CFC-11 as blowing agent in rigid polyurethane foams used as insulation in thermal tanks at TEM S.A.

220,300

The Executive Committee requested the World Bank to ensure that the old equipment replaced was disposed of in accordance with existing guidelines.

 

Elimination of the use of CFC-11 as blowing agent in rigid polyurethane foams used as insulation in cold storage and substitution of CFC-12 used as refrigerant with HFC-134a at Colder S.R.L.

325,070

The Executive Committee requested the World Bank to ensure that the old equipment replaced was disposed of in accordance with existing guidelines.