Decision in paragraph 130 in UNEP/OzL.Pro/ExCom/13/47

July 1994
Jordan
UNIDO
Projects approved / deferred / transferred

130.     The Executive Committee approved the following projects to be implemented by UNIDO and the funds indicated:

                                                                                                                                        Approved amount

                                                                                                                                                   (US $)

Phasing-out ODS at National Refrigeration Co.                                                              813,887

Phasing-out ODS at Middle East Electrical Industries Co. Ltd                                     883,153 

Phasing-out ODS at the Household Appliances Manufacturing Co.                           775,602 

Plus 13 per cent project support costs to UNIDO                                                          321,443