54. The Committee approved the following amendments to the 1994 UNDP work programme for a total amount of US$ÿ1,254,705, including US$ÿ185,705 as support costs for UNDP
.Country Project Approved amount US$
| Argentina | Project preparation assistance | ` | 70,000 |
| Conversion to non CFC technology in the manufacture of flexible and integral skin polyurethane foam at NSIPLAST | 345,000 | ||
| Institutional strengthening project (transferred US $359,500 from the World Bank) | 0 | ||
| Bangladesh | Project preparation | 35,000 | |
| Institutional strengthening under the Multilateral Fund for the Implementation of the Montreal Protocol | 150,000 | ||
| Jamaica | Project preparation assistance | 30,000 | |
| Mexico | Project preparation assistance | 100,000 | |
| Pakistan | Institutional strengthening projects | 259,000 | |
| Sri Lanka | Project preparation assistance | 30,000 | |
| Global | Determination of cost effective phase out approaches for enterprises with relatively small ODS use in foams | 50,000 | |
| Subtotal | 1,069,000 | ||
| 13 per cent project support costs | 185,705 | ||
| Total | 1,254,705 |