84.     The Executive Committee approved the following projects to be implemented by the World Bank and the funds indicated:

 

Approved amount

US $

Conversion to reduced CFC technology in the manufacture of Refrigerators at Refrigeracao Parana S.A., Unidade Sao Carlos

162,603

The Executive Committee noted that the company would not be seeking additional funding for conversion from the transitional substance. It also encouraged implementing agencies and Article 5 countries to avoid the use of 50 per cent CFC reduced technology in future projects.
Replacement of CFC-11/12 with cyclopentane/HFC-134a foaming agent/refrigerant in the manufacture of domestic refrigerators (Metalfrio S.A.)2,360,360
The Executive Committee noted that helium leak detector equipment at a cost of US $145,000 had been deducted from the above project and noted that incremental operating costs were being requested for a one-year period.