Project proposals: China
87. The Executive Committee approved the following projects to be implemented by the World Bank and the funds indicated:
Approved amount US $ | |
| Conversion to CFC-free technology in the manufacture of flexible polyurethane foam (slabstock) at Dongfeng Plastic Plant | 268,600 |
| Conversion to CFC-free technology in the manufacture of extruded polyethylene and polystyrene foam sheet at Lanzhou Plastic Packing Material Factory | 222,100 |
| Conversion to CFC-free technology in the manufacture of extruded polyethylene and polystyrene foam sheet at Cangzhou No. 2 Plastic Plant | 394,000 |
| Conversion to CFC-free technology in the manufacture of extruded polyethylene and polystyrene foam sheet at Zhengzhou Plastic Plant | 267,100 |
| Conversion to CFC-free technology in the manufacture of flexible polyurethane foam (slabstock) in Gaofeng Plastic Plant | 458,400 |
| The Executive Committee requested the World Bank to report on the issues relating to possible reduction in the project cost by avoiding the need to construct an extension to the factory premises. | |
| Conversion to CFC-free technology in the manufacture of flexible polyurethane foam (slabstock) at Beijing Foam Plastic General Factory | 720,000 |
| The Executive Committee requested the World Bank to explore the possibility of improving the production technology at the plant in a way that would lead to cost reductions by avoiding the need for a very high cost accelerated cooling system and to report to the Executive Committee regarding possible reduction in the project cost. |
|
| Conversion of medium-sized semi-hermetic CFC-12 air conditioning compressor production to HCFC-22 at Beijing Refrigerating Machinery Factory (GMRI) | 3,098,000 |