Decision in paragraph 93 in UNEP/OzL.Pro/ExCom/12/37

March 1994
World Bank
Projects approved / deferred / transferred

93.           The Executive Committee approved the following 1994 World Bank Work Programme for a total amount of US $2,743,000:

                 Project preparation                                         US $4,467,000

                Project supervision                                           US $  350,000

                Country programme preparation                    US $  344,000

                Administrative, legal and financial costs      US $1,119,000

                OORG                                                                   US $  300,000

                Total request                                                      US $6,580,000

                       Minus residual                                            US $2,100,000

                       Minus 1993 interest income                     US $1,737,000

                Cash requirement                                              US $2,743,000