Project proposals: Jordan
125. Investment project for phasing out ODS at:
(a) Household Appliances Manufacturing Co.;
(b) Middle East Electrical Industries Co. Ltd.;
(c) National Refrigeration Co.
The Executive Committee gave UNIDO permission to proceed. A one‑time request for operational costs should be submitted for consideration by the Executive Committee.
128. UNIDO would continue working with those countries [India, Egypt and Jordan] in accordance with the following:
(a) the cost should be brought down to a reasonable and agreeable level;
(b) cost reduction should not adversely affect the integrity of projects, particularly the safety aspects involved.
Following which, UNIDO could request the Executive Committee for an out‑of‑session approval of the projects so that momentum was not lost.