Decision 94/42

May 2024
Eswatini
UNDP | UNEP
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To approve, in principle, stage I of the Kigali HFC implementation plan (KIP) for Eswatini for the period 2024–2030 to reduce HFC consumption by 10 per cent of the country’s baseline by 2029, in the amount of US $163,850, consisting of US $115,000, plus agency support costs of US $14,950, for UNEP and US $30,000, plus agency support costs of US $3,900, for UNDP, as reflected in the schedule contained in annex XXXIV to the present report;
  2. To note that, upon completion of the end-user technology demonstration project included in stage I of the KIP, UNDP would submit a final report on the implementation of the project, including the HFC phase-out and energy-efficiency gains achieved, in line with decision 92/36(g);
  3. To approve the first tranche of stage I of the KIP for Eswatini, and the corresponding tranche implementation plan, in the amount of US $63,500, plus agency support costs of US $8,255, for UNEP; and
  4. To request the Government of Eswatini, UNEP, UNDP and the Secretariat to finalize the draft Agreement between the Government of Eswatini and the Executive Committee for the reduction in consumption of HFCs, including the information contained in the annex referred to in subparagraph (a) above, and to submit it to a future meeting once the KIP Agreement template had been approved by the Executive Committee.
Related annexes
Annex XXXIV to document 94/67, HFC phase-down commitments and funding tranches schedule under KIP for Eswatini