Decision 24/14

March 1998
UNDP | UNIDO | World Bank
Projects approved / deferred / transferred

Methyl bromide project preparation

Having taken note of the comments and recommendations of the Sub-Committee (UNEP/OzL.Pro/ExCom/24/17, paragraphs 24-31) on the 44 requests for project preparation funding for methyl bromide projects included in the 1998 work programmes of UNDP (UNEP/OzL.Pro/ExCom/24/21), UNIDO (UNEP/OzL.Pro/ExCom/24/23 and Corr. 1) and the World Bank (UNEP/OzL.Pro/ExCom/24/24), the Executive Committee decided to approve all requests other than those set out below. All approved requests for project preparation for methyl bromide are included in Annex V to the present report.

Related annexes
Annex V to document 24/47, approved projects and activities