Decision 24/9

March 1998
Project completion reports

The Executive Committee, having taken note of the Sub-Committee’s observations (UNEP/OzL.Pro/ExCom/24/4, paragraphs 26 to 27), decided:

(a) To approve the Format for Project Completion Report (Non-investment Projects), as presented in Annex III [to document UNEP/OzL.Pro/ExCom/24/47];

(b) That a project completion report should be submitted six (6) months after the completion of the project; and

(c) That the time schedule specified in Decision 23/8(k) for submitting completion reports for investment projects should also apply to non-investment projects, with an interval of three months to enable implementing agencies to prepare to use the new format.

Related annexes
Annex III to document 24/47, format for PCR (non-investment projects)