The Executive Committee decided:
- To approve, in principle, stage I of the HCFC phase-out management plan (HPMP) for the Gambia for the period 2011 to 2020 to meet the 35 per cent reduction in HCFC consumption, at the amount of US $233,300, consisting of US $110,000, plus agency support costs of US $14,300 for UNEP, and US $100,000, plus agency support costs of US $9,000 for UNIDO;
- To note that the Government of the Gambia had agreed to establish as its starting point for sustained aggregate reduction in HCFC consumption an estimated baseline of 0.92 ODP tonnes, calculated using actual consumption of 0.91 ODP tonnes and 0.94 ODP tonnes reported for 2009 and 2010, respectively, under Article 7 of the Montreal Protocol;
- To deduct 0.32 ODP tonnes of HCFCs from the starting point for sustained aggregate reduction in HCFC consumption;
- To approve the draft Agreement* between the Government of the Gambia and the Executive Committee for the reduction in consumption of HCFCs, as contained in Annex XVI to the present report;
- To request the Fund Secretariat, once the baseline data were known, to update Appendix 2-A to the Agreement to include the figures for maximum allowable consumption, and to notify the Executive Committee of the resulting change in the levels of maximum allowable consumption and of any potential related impact on the eligible funding level, with any adjustments needed being made when the next tranche was submitted; and
- To approve the first tranche of stage I of the HPMP for the Gambia, and the corresponding implementation plan, at the amount of US $82,750, consisting of US $25,000, plus agency support costs of US $3,250 for UNEP, and US $50,000, plus agency support costs of US $4,500 for UNIDO.
- This Agreement was revised as per Decision 71/30