The Executive Committee decided:
- To note the report on performance indicators contained in document UNEP/OzL.Pro/ExCom/71/17; and
- To modify the performance indicators established in decision 41/93, as modified by decision 47/51, as follows:
| Type of Indicator | Short title | Calculation | Weighting |
| Planning--Approval | Tranches approved | Number of tranches approved vs. those planned* | 10 |
| Planning--Approval | Projects/activities approved | Number of projects/activities approved vs. those planned (including project preparation activities)** | 10 |
| Sub-total | 20 | ||
| Implementation | Funds disbursed | Based on estimated disbursement in progress report | 15 |
| Implementation | ODS phase-out | ODS phase-out for the tranche when the next tranche is approved vs. those planned per business plans | 25 |
| Implementation | Project completion for activities | Project completion vs. planned in progress reports for all activities (excluding project preparation) | 20 |
| Sub-total | 60 | ||
| Administrative | Speed of financial completion | The extent to which projects are financially completed 12 months after project completion | 10 |
| Administrative | Timely submission of project completion reports | Timely submission of project completion reports vs. those agreed | 5 |
| Administrative | Timely submission of progress reports | Timely submission of progress reports and business plans and responses unless otherwise agreed | 5 |
| Sub-total | 20 | ||
| Total | 100 |